  • 84th St from STH 11 to Corliss Ave-create turning lane for commercial development
  • Willow Rd from STH 11 to northern Village limits(RR at SCJ)- repave 
  • 90th St railroad crossing culvert replacement and associated pavement and sidewalk repairs in project limits
Status Updates

Project Schedule

All dates and times are subject to weather delays-updates will be made if needed

84th Street

  • Remove concrete and excavation August 12th-19th
  • Concrete August 19th-30th
  • Loop detection-August 26th & 27th
  • Paving-September 3rd & 4th
  • Landscaping/Striping-September 5th & 6th

Willow Road

  • Pulverize-September 3rd
  • Excavation, base work-September 4th-12th
  • Loop detector-September 9th & 10th
  • Paving-September 16th-18th
  • Shouldering-September 19th & 20th
  • Guardrail install-September 23th & 24th
  • Landscaping-September 24th-27th

90th Street RR Culvert

  • Pavement removals-September 6th
  • Pipe installation-September 9th-11th
  • Excavation and base work-September 12th & 13th
  • Paving-September 20th
  • Striping and landscaping-September 23rd & 24th

 