Paving Areas:
- 84th St from STH 11 to Corliss Ave-create turning lane for commercial development
- Willow Rd from STH 11 to northern Village limits(RR at SCJ)- repave
- 90th St railroad crossing culvert replacement and associated pavement and sidewalk repairs in project limits
Status Updates
Project Schedule
All dates and times are subject to weather delays-updates will be made if needed
84th Street
- Remove concrete and excavation August 12th-19th
- Concrete August 19th-30th
- Loop detection-August 26th & 27th
- Paving-September 3rd & 4th
- Landscaping/Striping-September 5th & 6th
Willow Road
- Pulverize-September 3rd
- Excavation, base work-September 4th-12th
- Loop detector-September 9th & 10th
- Paving-September 16th-18th
- Shouldering-September 19th & 20th
- Guardrail install-September 23th & 24th
- Landscaping-September 24th-27th
90th Street RR Culvert
- Pavement removals-September 6th
- Pipe installation-September 9th-11th
- Excavation and base work-September 12th & 13th
- Paving-September 20th
- Striping and landscaping-September 23rd & 24th